Lewis County commissioners approve routine and contract items, including senior center repairs and road right‑of‑way acquisition
Summary
The Board of County Commissioners on March 11 approved a block of deliberation resolutions covering surplus vehicles, warrants and payroll, senior center change orders, public defender contracts and right‑of‑way acquisition for a culvert project. Several items were approved by unanimous voice vote.
Get email alerts on the County Administration Votes topic
No spam. Unsubscribe anytime.
The Lewis County Board of Commissioners on March 11 approved a package of notice, consent and deliberation items covering vehicle surplus, payroll warrants and several county contracts and change orders.
The board approved a notice item to surplus five county vehicles (resolution 25‑074) and a consent package including approval of warrants, payroll and minutes from the Feb. 25, 2025 business meeting (resolution 25‑066). The commission also recessed one item (resolution 25‑069) to a March 25 session.
Deliberation items approved by the board included:
- A request to ratify a contract amendment for the Toledo Senior Center renovation for $15,959.28 covering roof sheeting, fascia replacement and gutters (resolution 25‑070). - A change order for the Twin Cities Senior Center restoration in the amount of $26,426 for added roof insulation, removal of old gutters and installation of new gutters and screens (resolution 25‑071). - Approval of 2025 public defender contracts for superior, juvenile and district court services and authorization for the county manager to execute the contracts (resolution 25‑072). - Ratification of a contract between Lewis County Public Works and Sage Geotechnical for geotechnical and geological design services (resolution 25‑073). - Approval of right‑of‑way acquisition for the Evans Road culvert replacement at mile post 5.371 to comply with fish‑passable structure requirements (resolution 25‑075).
County staff described the surplus and change orders as routine replacements or necessary repairs. Public Works said a temporary culvert fix installed in 2022 requires a fish‑passable replacement within five years under current law, prompting the need for additional right‑of‑way.
All listed deliberation items (resolutions 25‑067 through 25‑073 and 25‑075) were moved and seconded together and approved by voice vote, 3‑0. Earlier motions to approve notice and consent items also passed 3‑0.
No substantive debate was recorded on most items beyond staff explanations. Commissioners asked staff for clarification about the timing for new dump trucks and for additional detail on the senior center roofing work; staff said installation schedules depend on vendor timelines.
Votes at a glance
- Resolution 25‑074 (surplus vehicles): approved 3‑0. - Resolution 25‑066 (warrants, payroll, minutes): approved 3‑0. - Resolution 25‑069 (recessed to March 25, 2025): approved 3‑0. - Resolution 25‑070 (Toledo Senior Center change order — $15,959.28): approved 3‑0. - Resolution 25‑071 (Twin Cities Senior Center change order — $26,426): approved 3‑0. - Resolution 25‑072 (2025 public defender contracts): approved 3‑0. - Resolution 25‑073 (Sage Geotechnical contract ratification): approved 3‑0. - Resolution 25‑075 (Evans Road right‑of‑way acquisition): approved 3‑0.
The meeting adjourned after the votes; the board did not take additional public comment on these matters after approval.