Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Quality topic

No spam. Unsubscribe anytime.

City study finds Swiss Village dirty‑water problem confined to one well; treatment cost deemed too high

2591782 · February 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A 2023 pilot study showed Swiss 2 well has elevated iron and manganese; staff recommended against a $12 million treatment system and favor drilling a new well at far lower cost.

Osage Beach — Public works staff reported Feb. 6 that a pilot study of the Swiss Village wells found elevated iron and manganese in one well (Swiss 2), and recommended against pursuing a roughly $12 million combined treatment system. Instead staff favor drilling a new production well at an estimated cost of about $1.18 million.

Operations manager Zach Wilbur described the SEH pilot study results. He said raw water averages from Swiss 1 and 3 were below the city’s operational targets for iron (0.3 mg/L) and manganese (0.05 mg/L), while the Swiss 2 well showed higher levels — iron near 0.2 mg/L and manganese averaging about 0.1 mg/L. “The studies showed that the raw water samples … Swiss 2 has the highest iron and the highest manganese load by far,” Wilbur said.

Treatment options and costs: The consultant’s recommendation was that oxidation, chlorination and green‑sand filtration could reduce metal residuals to nearly unnoticeable levels. However, the estimated total project budget was roughly $12,000,000; staff told the board that cost did not justify treating a single problematic well.

Operational choice: Because Swiss 2 has been placed in emergency status and is used only when needed, dirty‑water calls have dropped since the change. Staff recommended drilling a replacement well — estimated at about $1.18 million — as a more cost‑effective long‑term solution. The board signaled consensus with the new‑well approach during the department update; no formal vote was required.

Technical and service implications: Staff noted Swiss 1 and 3 cannot alone carry peak summertime demand without multiple pumps; Swiss 2 remains available as an emergency backup if needed. If the city later adds a third or fourth well, staff said they could remove and properly abandon Swiss 2.