Council approves Ameren substation improvements on Olive Boulevard with floodwall and sidewalk repairs

2591614 · February 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a site plan for Ameren’s substation at Olive and Waldron that includes new floodwalls, drainage work, landscaping and a repaired sidewalk; Ameren said a permanent floodwall will remove the need for 24-hour security guards.

University City’s City Council approved a site-plan application for Ameren’s substation at Olive Boulevard and Waldron on Feb. 10, 2025, authorizing floodwalls, drainage improvements, new landscaping and sidewalk repairs.

Planning staff Dr. Wagner described the application as site-plan approval for the Ameren substation across from Heman Park. He said the project adds floodgates and flood walls, improves drainage and will add landscaping.

Scott Vilbig, representing Ameren Missouri, told council the plan includes replacing the gravel drive with concrete and repairing the sidewalk in front of the site. He said temporary 24-hour security guards are in place now because equipment was lost during the 2022 flooding; the planned floodwall will serve as permanent site security, and Ameren will remove round-the-clock guards once the wall is built.

Council member Clay praised Ameren’s community outreach to councilmembers and neighbors. Council moved to approve the site plan; Council member Fuller made the motion and Council member Smotherson seconded. The motion passed by voice vote.