Facilities director details courthouse, HVAC and elevator work, Professional Building demo and other capital projects

2585024 · March 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities reported on HVAC and chiller replacements, elevator upgrade schedule, courthouse clock-tower repairs, demo and abatement at 93 Public Square, auctioning of excess furniture and ongoing bids for building projects.

Steven Bastine, representing Facilities, provided a multi-site facilities update covering HVAC and chiller work, elevator replacement scheduling, courthouse and Professional Building activity, and other county-owned facility maintenance.

Why it matters: Several capital projects—including HVAC replacements, elevator upgrade and demo of 93 Public Square—affect public access to buildings and require coordination to limit service disruptions and manage contractor schedules.

Key items Bastine reported include: installation of Geotab GPS devices on maintenance vehicles; Columbia Gas scheduled to install gas lines and rooftop unit work at 60 Public Square; a crane visit and schedule for removing and replacing a chiller unit (work to take a few hours on a weekend); auctioning excess furniture at 72 Public Square and other buildings with recycling or disposal of unsold items; vestibule door installation at Administration Building Entrance B and planned garage-door replacement at that site; ongoing interior bathroom/plumbing and flooring renovations timed to precede an elevator upgrade (the elevator overhaul is scheduled for May and estimated to take six weeks with a contingency to push back if needed); demo and abatement of 93 Public Square has begun; RTU and AHU replacements and condensate issues at the jail are under investigation; and some RTU/regulator issues at the soil and water administration site remain under repair.

Bastine said the Facilities team met with architects to review the County Home dining-room footers and that new electrical panels were installed at the County Home to restore fire-suppression functionality. He noted coordination needs with tenant events (a Memorial Day weekend dance show) and indicated contractors (including Kone elevator) have agreed to schedule flexibility if the county requests it.

Ending: Commissioners asked about timing and contingency plans for elevator and bathroom work and thanked Facilities staff for progress updates; the Professional Building recently had a bid opening but no award decision was made during the meeting.