Podunk and other bridge projects delayed by historic-preservation review; rehab option under study
Summary
County engineers told the committee that several bridge projects, including Podunk Road and Freeze Road, have been slowed by cultural-resources review and historic-designation issues; staff are exploring rehabs and storage or re-use as alternatives.
Get email alerts on the Infrastructure Bridges topic
No spam. Unsubscribe anytime.
Tompkins County Highway officials told the Facilities and Infrastructure Committee on Feb. 20 that several bridge projects are delayed by federal and state cultural-resources reviews and historic-preservation determinations, and that the county is exploring rehab options and storage or transfer of historic truss bridges.
The Podunk Road bridge project "was caught up in Cultural Resources Section 106," Jeff (Highway Department) said, and that process had been "painfully slow going." He said the county has been working closely with consultants and NYSDOT but remains stuck in the historic-review phase. Jeff noted the county previously stored redundant bridges in local yards for future re-use, but recent changes have limited that option.
The committee also discussed the West Cortland Street Bridge, where bids came in significantly above engineer estimates and the county is now considering a targeted rehabilitation rather than full replacement. "We just didn't have enough funding at the time," Jeff said of the earlier effort to fully replace the bridge; he added the county will analyze which components have useful life and which need attention and that a substantial rehab could buy roughly 20 years of service.
Bridge NY funding was discussed as well. Jeff said the five-year Bridge NY program allocated its funds across rounds and that the county hopes for another round, but that scoring formulas sometimes make specific bridges poor candidates.
Ending
Staff said they will return with more detailed cost estimates and a plan for next steps after final engineering assessments and continued coordination with historic-preservation reviewers.