DOTD outlines strategic improvement plan after Boston Consulting Group review
Summary
DOTD staff described a strategic improvement plan in response to a Boston Consulting Group benchmarking review, including organizational changes, new KPIs, rule revisions and a data governance effort intended to improve project delivery and transparency.
Get email alerts on the Dotd Strategic Improvement Plan topic
No spam. Unsubscribe anytime.
Department of Transportation and Development officials updated the joint House and Senate Transportation Committee on a strategic improvement plan the department developed in response to a Boston Consulting Group (BCG) benchmarking review.
DOTD staff said the strategic plan targets on-time project delivery, organizational realignment, clearer rules and permitting, data governance and the development of measurable key performance indicators (KPIs). "We were very candid with BCG," a DOTD official told the committee, describing a collaborative review that informed the department's action plan.
Why it matters: the BCG review and DOTD's response were framed as a prerequisite to asking for larger, recurring funding. Committee members and industry witnesses have linked accurate delivery forecasts and transparent performance metrics to the willingness of legislators and the public to approve additional transportation revenues.
DOTD described several concrete items in its plan. The department has begun publishing a 180-day letting list with the near-term goal of producing a one-year letting list that is nearly 100% accurate. DOTD said some changes will require civil-service coordination or legislative action; an example offered to the committee was moving non-road functions such as certain public-works and drainage programs out of the Office of Engineering, which would require statute changes to Title 36.
The department also told members it will revise regulations and manuals and issue notices of intent to amend three rules: access permits, tandem-truck permit regulations and vegetation controls. DOTD said it will run a comprehensive three-year review of all manuals and policies, and that the first rule amendments should be published as notices of intent within weeks.
DOTD said the agency is contracting for data-governance work and plans dashboards and public viewers to provide the public and the Legislature clearer, single-source answers to common questions, such as mileage on the state system. The committee heard that DOTD has roughly 4,300 full-time positions and that agency turnover varies by job class; an agency-wide engineering turnover rate was reported to be about 7.21%.
On staffing and pay, the department told the committee that pay-source rules and historical funding choices complicate efforts to equalize salaries. DOTD highlighted an Attorney General interpretation that has led it to pay salaries and benefits with Transportation Trust Fund money rather than the general fund, a situation the department said constrains how it can deploy pay adjustments without reducing project funding.
Ending: committee members welcomed the strategic plan but said more transparency and quicker public reporting will be necessary for legislators to judge the effectiveness of reforms. DOTD committed to publishing more detailed KPIs and to continuing monthly briefings to the committee.