Change order sought after asbestos, lead found in annex flood remediation; county will seek recovery from roofing vendor

2567874 · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Finance staff said a contractor discovered asbestos and lead during flood mitigation at the county annex, producing a $23,007.46 change order that will increase the emergency-authorized estimated contract to about $153,003.51; the county will first seek recovery from the roofing vendor and may file a claim with the county risk pool if necessary.

Cowlitz County finance staff told commissioners the contractor performing flood mitigation at the county annex discovered asbestos-containing floor tile and lead during work, requiring an abatement change order and additional finishing work.

Finance Director Cathy Funk Baxter said the remediation contractor, Prestige Northwest Construction Services, completed mitigation and then uncovered asbestos and lead that were not included in the original contract. The recommended change order totals $23,007.46, bringing the new estimated contract value to $153,003.51. The original emergency purchase authorization totaled $140,000.

Baxter described the additional work as abatement and related masking, drywall, texture, priming and painting needed after hazardous materials were removed. County staff said they will seek recovery from the roofing vendor that caused the leak and flooding; the county’s risk pool will assist and the county would file a property claim with the risk pool only if vendor recovery efforts are unsuccessful.

Why it matters: the change order increases the contract cost above the emergency authorization amount and triggers a recovery effort against the roofing vendor. The work involves hazardous‑materials abatement and related repairs that affect closure of the annex remediation project.

Ending: The change order and revised contract total will be presented to the board at the next meeting as a motion item for approval.