Engineer says Bell Road East paving pushed to ODOT 2026 schedule; village to extend OPWC grant request

2564595 · March 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Village engineer told council Bell Road East design will finish in 2025 but construction is now scheduled for ODOT's 2026 bidding cycle; village will request an OPWC grant extension and split local costs between 2025–26.

The village engineer updated council on Bell Road East, saying design and ODOT coordination will finish this year but construction is now set for ODOT's 2026 cycle, and the village has requested an extension of its OPWC grant.

The engineer said design completion is anticipated by Aug. 15, with the project entering ODOT's bidding cycle beginning Dec. 1, 2025, and a planned spring 2026 construction start with a projected completion by Oct. 31, 2026. The engineer characterized the NOACA funding split as an "80/20 split" and said the village expects to spend about $120,000 in 2025 for design work and ODOT coordination; the larger construction share would be paid in 2026.

The engineer said he submitted a request to extend the OPWC (Ohio Public Works Commission) grant through the end of 2026 so the grant will still apply to construction. He said he did not expect difficulty securing that extension but had not yet received confirmation.

Council members asked whether interim pavement repairs were needed, and the engineer said temporary patching will be required to preserve the roadway surface until full paving work occurs. The engineer also advised that some culvert work previously budgeted was completed; other minor culvert work remains.

Separately, the engineer said he plans an OPWC application in the current round to combine storm-sewer rehabilitation on Hazelwood with paving, to improve the village's chance of receiving construction funding by classifying the application as a hard infrastructure project.

Ending

Council directed the streets and public utilities committees to weigh local road program priorities for 2025–26 given the shifted Bell Road schedule; no final reallocation decision was recorded at the meeting.