Board approves design and early procurement for roofs and South Addition; authorization includes ~$6 million early work
Summary
The board approved amendments to design and bidding work for roof replacements, authorized early procurement and a guaranteed maximum price (GMP) for site work tied to the South Addition (approx. $6 million for early packages), and approved work to replace three high-school scoreboards. The items passed 5-0.
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
The Dublin City Schools board approved several facilities actions Monday, authorizing additional design and procurement work for roof replacements, early site work and equipment procurement for the South Addition project and replacement of three high-school scoreboards.
Operations Director Mr. Stark described a program of roof assessments and repairs driven by earlier limited warranties and wet insulation issues. The district retained May's Consulting to assess roofs and prepare bid documents; the board approved an amendment to that contract to design and RFP roof work that cannot wait until the larger 2026 bid cycle. Mr. Stark said two Kauffman High School roofs were identified as needing urgent replacement because they include skylights and window connections that require immediate engineering and replacement.
The board also approved the first guaranteed maximum price (GMP) related to the South Addition project with Robertson Construction. Mr. Stark said GMP No. 1 covers primarily site work and early procurement of long-lead items such as HVAC equipment and electrical distribution panels; he estimated the early procurement/GMP package at approximately $6,000,000, subject to city permits and schedule. If permits proceed on schedule, the district expects to break ground in April and to manage subsequent GMPs as the project progresses.
Finally, the board approved design and public-bid work to replace three internal scoreboards (one at each high school). Mr. Stark said the existing scoreboards are more than a decade old; replacing all three this calendar year will simplify maintenance and solve software and parts issues.
Board action: The superintendent recommended approval of items 11a through 11d (roof assessments/RFP design amendments, GMP No. 1 for South Addition early packages, and scoreboard work). The board approved the package by a 5-0 vote.
Why it matters: The approvals fund immediate repairs for aging roof systems and commit early funding to a major building addition; the GMP includes early procurement that reduces schedule risk for long-lead mechanical and electrical components. Board members asked about schedule and permitting; staff reported confidence that permits and site work can proceed in time for the intended ground-breaking.
Ending: Projects will proceed into procurement and public bidding phases; the district will return with further GMPs and contract documents as work advances.