Public works: Bridgeport sewer backup cleared; Barnell relief sewer permitting in progress
Summary
Council was updated on a full sewer blockage that flooded basements in Bridgeport, and staff said they are preparing EPA and sewer-district permit materials for the Barnell relief sewer project.
Get email alerts on the Infrastructure Sewer topic
No spam. Unsubscribe anytime.
Public Works Director Mr. Cooney told the council that crews and the county responded to a major sewer backup in the Bridgeport housing cluster; the line on Lander near Landerbrook was found to be 100% blocked and the county cleared the blockage at about 5:00 a.m. that day.
"The county did clear it about 05:00 and now we're trying to figure out if it's a broken pipe or what's going on. But it's a county issue and they were very responsive," Mr. Cooney said. He noted several basements in Bridgeport suffered backups as a result of the blockage.
On the Barnell project, Cooney said staff are adding laterals to the plans and have submitted a hydraulic study to the sewer district; he expects to submit an EPA permit application by the end of next week and anticipates a four- to six-week review period. He said relocation of a gas line and coordination with the county water department are ongoing, and that construction is planned for summer subject to permit approvals.