Board approves stadium and middle/high‑school change orders; gas‑line relocation, scoreboard fiber and electrical work funded from project accounts

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities committee presented several change orders for the middle/high school and stadium construction; the board approved electrical and scoreboard fiber change orders and authorized UGI gas‑line relocation work to accommodate the new parent loop access road.

The board approved three project change orders tied to the district's middle/high school and stadium work: electrical upgrades to meet code, fiber conduit work to the scoreboard, and a required gas‑line relocation along Everly Drive.

Facilities staff reported that some work fell outside the original scope and had to be added after field inspections. The board voted to approve a $31,129 electrical change order for code compliance and a $12,787 change order to run fiber from the press box to the scoreboard; the scoreboard change includes work the vendor excluded from its supplier scope. Administrators said a $15,000 credit from the scoreboard vendor offsets part of project costs and that both items will be paid from the middle/high school project budget.

Separately, UGI (the gas utility) identified that an existing gas main crossing the planned parent‑loop entrance near the barn sits too shallow for the new road and must be lowered roughly three feet across a 40‑foot run. The board authorized the $8,531.92 estimated relocation cost so the parent loop can be constructed; facilities staff said this expense was not previously budgeted and will come from the project contingency or related project funds.

Facilities committee members also reported ongoing items including a proposed bucket truck purchase for maintenance (committee recommendation; cost approximately $8,000) and a sprinkler system replacement at Nancy Grayson Elementary that staff will present with funding options. The administration told the board that most stadium and field punch‑list items remain on schedule and that the contractor expects construction completion ahead of the new school year, with specific work (for example, throw‑circle concrete and scoreboard wiring) scheduled to align with press‑box and scoreboard installation.

Board members pressed for more complete, approved prints before future bid packages after noting prior change orders were partly driven by incomplete drawing sets. Staff agreed to tighten document control for future solicitations.