Engineering update: Warehouse 300 ribbon cutting, BT1 electrical work and shiploder commissioning continue
Summary
Engineering staff reported a ribbon cutting for Warehouse 300 (replacing seven small warehouses), ongoing electrical turnover at BT1 to support new dock equipment, shiploder 3 commissioning progressing, and the Industrial Canal project expected to go out for bid next month.
Get email alerts on the Warehouse 300 Engineering topic
No spam. Unsubscribe anytime.
Engineering and maintenance staff updated the board on construction and equipment projects across port facilities, including the Warehouse 300 ribbon cutting and ongoing commissioning work at BT1.
Mister Nick reported that Warehouse 300 replaces seven smaller warehouses (each about 24,000 square feet) and that the ribbon cutting was held recently. He said electrical work at BT1 required a seven‑day shutdown to transfer power to newly installed gear that will support new dock loading and unloading equipment. Shiploder 3 commissioning was progressing and work continued around the clock while power transfers were scheduled.
Nick also said construction at City Docks and Sallier Rail is advancing; Sallier Rail is close to completion and the city is expected to begin an associated road project. He told commissioners multiple bid openings are scheduled for the next meeting, primarily for equipment purchases with several construction awards to follow. Nick confirmed the Industrial Canal design (discussed elsewhere on the agenda) is expected to go out for bid next month.
Commissioners commended staff on the ribbon cutting and asked routine questions about project timing. Staff named Albert Palma and Chuck Myers and Associates as engineers involved in Warehouse 300 design and construction.