Administrators presented estimated costs to pilot one full-size electric school bus. A quoted vehicle price was $504,000 with a New York school bus incentive (NYSFIP) voucher that could reduce net bus cost to about $246,000; diesel buses cost roughly $162,000 each. Charging hardware/install could be covered by vouchers but software, network and
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
District officials presented preliminary numbers for a one-bus electric pilot and advised the board to start the voucher application process to secure state incentives while the district completes a broader feasibility study.
Cost estimates presented A transportation/operations presenter told the board a full-size electric bus quote from the vendor was $504,000. The New York School Bus Incentive Program (NYSFIP) voucher cited in the presentation could reduce the bus price by about $257,000, lowering the bus purchase price to roughly $246,000. By comparison a diesel bus quote was cited at approximately $162,000, making the sticker-price difference about $84,000.
Charging infrastructure and incentives The presenter said vouchers could also cover charger hardware and installation costs; however networking and annual charging software fees were estimates and listed as to-be-determined. For a single-bus pilot, the presenter said the district would likely not need a large utility service upgrade. Some installation and software costs may be eligible for transportation aid reimbursements.
Board discussion and risk notes Trustees asked about total lifecycle costs, maintenance and insurance. Board members noted other districts’ experience: one nearby district (Chatham) had reported procurement, repair and service delays for multiple electric buses, and trustees expressed concern about vendor support and the technology’s operational maturity. Several trustees also said the state mandate and timelines for electrifying bus fleets (discussed broadly in the meeting) make it prudent to explore a pilot, while others warned about cost and reliability risks.
Administration recommended next step Officials recommended starting the NYSERDA voucher application promptly to preserve eligibility and noted that voter approval would still be required for any bus purchase in a bus-proposition ballot. The board directed administrators to move forward with voucher paperwork and to bring fuller lifecycle cost and maintenance estimates, insurance impacts and community briefings before voting on a bus proposition.