Council approves change orders for Safe Routes to School project; city to pay $7,700, water district to reimburse other costs
Summary
East Wenatchee approved three change orders for its Safe Routes to School project, authorizing the mayor to sign change orders 6–8 with Active Construction Inc.; the city’s direct fiscal impact is an estimated $7,700 for a concrete driveway conversion, with other increases paid by the East Wenatchee Water District.
Get email alerts on the Safe Routes To School Change Orders topic
No spam. Unsubscribe anytime.
The East Wenatchee City Council on March 4 approved Resolution 2025-16 authorizing the mayor to sign change orders 6, 7 and 8 with Active Construction Inc. for the Safe Routes to School project (City project numbers 2019-08 and 2019-09).
A city staff presenter explained the change orders are subject to council review because the city’s finance policy requires council approval for any change order that increases a contract by more than $100,000 or 10 percent, whichever is lesser. Most of the costs in the three change orders will be borne by the East Wenatchee Water District, the presenter said; only one item — changing a driveway from hot-mix asphalt to concrete — will be charged to the city, at about $7,700.
Staff said the other changes included extending a 12-inch water main at the Jonathan and Fifth intersection to avoid cutting into a new intersection on a future project, and replacing pavement after a contractor repaired a leaking valve. The water district requested several items during construction; the project agreement included $100,000 from the district toward their improvements.
Council member Tidd moved approval and council member Magdoff seconded. The council voted in favor; the motion carried. The presenter noted the city will pay the contractor the full contract amount and be reimbursed by the water district for district-paid items.