Board discusses administration relocation, leasing costs and grade-band trade-offs as part of master facilities study
Summary
The Facilities Committee spent a large portion of its March 6 meeting on districtwide master-plan trade-offs: whether and how to move central administration, leasing alternatives and whether to change grade bands.
Get email alerts on the Master Plan Administration Grade Bands topic
No spam. Unsubscribe anytime.
The Facilities Committee spent a large portion of its March 6 meeting on districtwide master-plan trade-offs: whether and how to move central administration, leasing alternatives and whether to change grade bands (for example, moving to 6–8 middle schools).
Tony Rafter, the district’s director of business administration, summarized administration-space options and reported preliminary market feedback from a local commercial broker. Ray Jones — a broker cited in the meeting — supplied three leasing price examples that district staff described at the meeting: approximately $855,000 per year for a roughly 30,000-square-foot building (about $28.50 per square foot), about $637,000 per year for a 26,000-square-foot building (about $24.50 per square foot), and roughly $638,000 per year for a 29,000-square-foot building (about $22 per square foot). Staff noted that typical commercial leases for a renovated, customized administrative space are generally structured with multi-year terms; the broker advised five-year leases as common for customized tenant improvements, though shorter temporary occupancy options are sometimes available for one-year needs with limits on tenant improvements.
As part of the master-plan discussion, staff presented alternatives for where to locate administration if Chancellor were vacated for renovation: renovate the Chancellor Center, convert 35,000 square feet in Wrightstown or Richborough into administration, or lease external space. Consultants gave order-of-magnitude renovation and new-construction numbers: fully renovating 35,000 square feet at a high level (using $450–$600 per square foot assumptions for new or surgical additions, and $250–$350 per square foot for renovation) yields different budget profiles; staff cautioned these are order-of-magnitude estimates only.
The committee also reviewed two districtwide grade-band approaches: (1) shift to a 6–8 middle-school model by adding capacity (presented as two 500-student additions to the middle schools), which consolidated sixth grade into middle schools and would add substantial capacity at the elementary level; or (2) retain the current grade bands and target renovations and selected elementary additions where the demographer forecast overcrowding (Newtown, Welsh, Sol Fine Stone and Wrightstown). Consultants said the 6–8 scenario can free up roughly 750 seats across elementary schools in the medium term, reducing the immediate need for large elementary additions. The committee heard that academic and operational work would still be required to implement any grade-band change and that some curricular and staffing transitions would require a year of planning and at least one summer to implement.
Officials and board members discussed other revenue planning to pay for the multi-year capital program. The district’s current uncommitted borrowing capacity was discussed; staff noted that borrowing capacity increases in future years as other district debt drops off and that modest annual increases to debt service (for example, planned tax-rate adjustments over multiple years) can be used to smooth borrowing needs. Board members asked staff to produce a clear borrowing/phasing plan that ties specific project bundles to realistic financing scenarios.
Ending: The facilities and finance staff will produce clearer, itemized renovation and lease-cost packages, more precise borrowing scenarios and an education-committee discussion on the instructional impacts of any grade-band change. The board did not make a final decision on grade bands or administration relocation at the meeting.