High school entrance redesign to add secure reception, SRO office and finishes; demolition set to start after graduation
Summary
Superintendent Dr. Hall provided an update on a planned high school safety renovation: secure double‑entry with a receptionist area, SRO office, new finishes and demolition scheduled to begin the weekend after graduation.
Get email alerts on the School Safety topic
No spam. Unsubscribe anytime.
Superintendent Dr. Hall updated the board on the Pendleton Knights High School safety renovation scheduled for the summer. The design replaces the existing entrance with a secure double‑entry vestibule directing visitors through the reception area and adds a School Resource Officer office with an exterior window for better visibility.
Dr. Hall displayed finish options for the reception area and said the project includes luxury vinyl tile in high‑traffic areas and carpet elsewhere. He noted a large painted horse statue at the high‑school entrance must be relocated within the building because it conflicts with the new doorway configuration; he emphasized the statue would be preserved and relocated rather than disposed of.
The project was put out to bid and will be advertised in two newspapers with a contractor walk‑through to follow. Bids will be opened on April 3, a board meeting night, and the administration expects to present bid results to the board in May. Demolition is scheduled to start June 5, after graduation, and the administration said the schedule is intended to minimize disruption to school events.
Board members praised the design and compared it to successful layouts at other districts; the board did not take a formal vote at the update.