Duval project: board hears construction update, contingency funding and upcoming change order

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board members were updated on the Duval construction project, including site drainage work, blasting completed, footers scheduled to start Jan. 27 and about $308,000 remaining in contingency; a change order will appear on the next meeting agenda.

Board members heard an update on the Duval construction project at the January meeting. The district reported significant site work, drainage installations and foundation preparation, and signaled a change order will be presented at the next board meeting.

A board speaker said there remains "$308,000 in the contingency, in the budget that we have left at our disposal," and that a change order related to recent work "will be coming up on the next board meeting." The speaker described the current site work: contractors have completed blasting for footers, drainage trenches about "10, 15 foot deep" and roughly "20, 25 foot wide" from the road to the hillside, and installed multiple large-diameter pipes that are connected to manage runoff.

The speaker said crews were placing gravel and mesh over the site and that weather permitting, footer work would begin Jan. 27. The speaker described the installed drainage as functioning like "a giant leach bed" to collect runoff and channel it under the road into a nearby creek. The board was told masons have been contacted and plans include laying a cornerstone.

The remarks were descriptive; no formal action or vote on the change order was recorded at this meeting. The board was told the change order will be on the next meeting agenda for consideration.