Onalaska committee approves bids, consultant selection, pavement maintenance and contract date extension; all votes unanimous
Summary
The Onalaska Board of Public Works and Utilities Committee awarded multiple contracts and approved pay estimates and a contract completion-date extension during its March 4 meeting; all recorded votes were unanimous.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
The Onalaska Board of Public Works and Utilities Committee on March 4 approved a slate of routine contracts, consultant selections and pay estimates in unanimous votes, including a single-bid concrete contract, a 2025 urban forestry contract, consultant selection for County Road SS, the 2025 pavement maintenance chip-seal program and a contract-completion extension for the Franklin Street lift station project.
Motions were largely procedural and carried without recorded opposition. The committee also approved the meeting minutes and 16 pay estimates.
Votes at a glance
- Minutes: Approved minutes from the previous meeting. Motion by Sabrina Steger; second by Jared Holter. Outcome: Approved (unanimous).
- 2025 Miscellaneous Concrete (single bid): Awarded to Fowler and Hammer for a base bid of $298,592.03. Motion by Jared Holter; second by Sabrina Steger. Outcome: Approved (unanimous). Notes: One bidder met requirements; three contractors inspected the project prior to bidding; the award falls within the project budgeted amount (~$315,000).
- 2025 Urban Forestry: Awarded to Krebeck Holdings LLC for $59,430. Motion by Jared Holter; second by Sabrina Steger. Outcome: Approved (unanimous). Notes: The project is budgeted at $80,000; the city expects a $25,000 reimbursement from the Wisconsin Department of Natural Resources after project completion. Staff stated a $50,000 minimum spend is required to receive the full $25,000 grant.
- County Road SS professional engineering services (design): Awarded to SEH for $89,800. Motion by Jared Holter; second by Sabrina Steger. Outcome: Approved (unanimous). Notes: Two firms submitted proposals (SEH and MSA). SEH scored higher in the committee's evaluation. The 2025 capital improvements budget included $75,000; staff said remaining design budget will be programmed in 2026 and the project will span nearly two years to complete design and state review.
- 2025 Pavement Maintenance (chip seal): Approved to proceed at an estimated cost of $395,837.02. Motion by Sabrina Steger; second by Jared Holter. Outcome: Approved (unanimous). Notes: The city will again contract with La Crosse County for chip-seal work; staff used an estimated unit cost of $1.82 to compute the total. The 2025 CIP budget includes $400,000 for this work.
- Franklin Street lift station rehabilitation (Change Order No. 1): Approved a contract completion date extension for TJ's Excavating from May 1, 2025, to November 1, 2025, with no cost change. Motion by Sabrina Steger; second by Jared Holter. Outcome: Approved (unanimous). Notes: Staff attributed the extension to long lead times on specified valves and supply-chain delays; Wisconsin DNR (Clean Water) staff approved the revised completion date.
- Pay estimates: The committee approved 16 pay estimates as presented (including a corrected contract amount for Municipal Well & Pump of $80,100 and payment for a delivered generator to TJ's Trucking). Motion by Steven Knott; second by Sabrina Steger. Outcome: Approved (unanimous).
Several agenda items were informational only, including an update on the Wisconsin Department of Transportation State Trunk Highway 157 (Main Street) project, which staff said remains on track for construction in 2028 and will have a public information meeting in spring/summer 2025.
No members of the public spoke during the public-input period at this meeting.