Utility undergrounding Phase 1 reaches 25% construction; planning underway for additional phases
Summary
Contractor has installed conduit and equipment placement is substantially complete on the north side of Highway 98; city staff and consultants outlined timing, permitting and potential funding sources for future phases.
Construction crews have completed significant work on Phase 1 of Destin’s utility undergrounding project on Highway 98, city staff and project manager Stephanie Lindsay reported at the March 3 council meeting.
Phase 1 progress: "As of January 29, the project's total construction was at 25 percent complete," Lindsay said, adding that conduit on the north side of Highway 98 between Beach Drive and the bridge is installed and equipment placement was approximately 95% complete. She also said the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat