Council approves OHM change order that returns $80,350.98 to roads budget

2498815 · March 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Milford City Council approved OHM change order No. 2, which required additional rehabilitation early in the project and resulted in a net return of $80,350.98 to the project budget.

Milford City Council approved OHM Change Order No. 2, which officials said addressed additional roadway-edge and curve rehabilitation discovered early in the project and returned $80,350.98 to the project budget.

City staff said the extra work—done to avoid premature pavement failure—was identified at the start of construction and engineered with input from the contractor and the city team. A presenter described coordinated work by the contractor, city staff and the project engineer and said the project still came in under budget by $80,350.98.

Council members asked about coordination with utility companies after the presenter noted a 1929-era utility line was discovered and that the city has had trouble getting timely planning-side engagement from DTE. The presenter said the city has had better responses from DTE Electric than from DTE Gas and that field contacts have promised follow-up names for planning coordination.

The council moved and voted to approve the change order during the meeting; the motion carried.

The approval included no amendment to the project scope beyond the additional rehabilitation identified at the site. No future funding or schedule changes were specified in the city presentation.