Council advances city‑county sewer work, authorizes nearly $6.93 million to close Dairy Lane project

2495361 · March 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Ordinance 26‑25 was read for the first time on March 3 to allocate $6,930,801 across street, water and sewer funds to complete the Dairy Lane/Stagecoach sewer expansion as part of the City‑County sewer expansion; council heard administration say sewer fund can absorb the cost.

Athens City Council read Ordinance 26‑25 on March 3, which would appropriate an additional $6,930,801 for the City‑County sewer expansion and related projects, including final work on the Dairy Lane/Stagecoach sewer segment.

Section 3 of the ordinance describes how the $6,930,801 would be expended: $285,000 from the street fund (220) for sidewalk design and construction; $1,351,306 from the water fund (740) for water line construction, construction engineering and contingency; and $5,294,495 from the sewer fund (750) for sewer easements, construction, construction engineering and loan fees. The ordinance was presented in committee and read for the first time at this meeting.

Council members asked whether the sewer fund could handle the appropriation; Mayor Patterson said the sewer fund can handle the additional expense. The presenter said this is intended to be the final allocation needed to complete the long‑running projects 03/17 and related project 03/30.

Because the item was read for the first time at the March 3 meeting, it will return for further consideration in subsequent meetings per council rules. The ordinance will require future votes for final adoption and appropriation of funds.