Council approves amended award for RFP 2507 to construct new 24/7 recycling center after negotiation
Summary
Council approved an amended award for the recycling center construction project after staff negotiated items out of the bid and reduced the award to $161,645.21. The project uses an ADA recycling grant and will be built on a vacant lot at Raley Road and Texas Avenue.
Get email alerts on the Recycling Center topic
No spam. Unsubscribe anytime.
The Alexander City Council on March 3 approved an amended award for bid number 2507 to build a new recycling center, lowering the amount from an earlier figure to $161,645.21 after the public works director negotiated removal of items outside the bid specifications.
Staff told the council they had pursued an ADA recycling grant, originally seeking approximately $104,000 in grant funds and receiving bids that varied widely. During pre-award negotiations, the city removed items the contractor could complete outside the bid specifications, which reduced the construction award to $161,645.21. The council approved the amended resolution by roll call; the vote was unanimous.
Drew, speaking for staff, said only two bids initially met specifications, one about $330,000 and another around $190,000; negotiations removed nonessential items such as spray-foam insulation to reduce cost. The city plans to build the recycling facility on a vacant lot at the corner of Raley Road and Texas Avenue, provide 24/7 citizen access outside the fence, and incorporate features to allow weekend access. Staff said the vendor has a four-week lead time to receive the building after a notice to proceed and that the city will issue the notice and give the contractor six weeks to start on site.
Councilors expressed appreciation for the recycling-site staff and the on-site attendant’s work. The council also amended the resolution’s budget language to change a referenced $108,000 figure to $104,110 (as recorded in the motion) and then voted to approve the award as amended.
The resolution names the contractor as J. Manuel Constructions LLC in the agenda language; a motion in the meeting referenced “Jay Manifold” during discussion. The record shows the award as amended to $161,645.21.
Construction timing: staff said the manufacturer has a four-week lead time for the building and the city will issue a notice to proceed and allow six weeks for the contractor to mobilize. No building permit or construction contract beyond the bid award was signed at the meeting.