CSO pump station delayed by National Grid work; Bennett Street 72-inch pipe installation underway
Summary
Commission staff said phase 3 pump-station commissioning is delayed by electrical work with National Grid and remains 2–3 months from testing; phase 4–5 work on Bennett Street is installing 72-inch and 60-inch pipes and the western interceptor lining contract is about 46% complete.
Lynn City Water & Sewer Commission staff briefed commissioners on combined-sewer-overflow (CSO) work, saying electrical connections with National Grid are slowing the phase 3 pump-station schedule and that major pipe installations on Bennett Street are progressing.
"We're still working with National Grid to get this thing fired up," Anthony, a staff member, said of the phase 3…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat