Commission staff said the $72 million wastewater treatment rehabilitation is progressing and on schedule for a July 1 completion, but the city—s water supply is at 54% of capacity—well below the seasonal average of about 77%—prompting contingency plans to start an additional pump station if rain arrives.
Lynn City Water & Sewer Commission staff reported that the multi-year rehabilitation of the wastewater treatment plant is progressing and remains on schedule, while the city is coping with below-average water-supply levels.
Anthony, a staff member, told commissioners the dewatering building and a screening structure are nearly finished, and that the larger wastewater rehabilitation contract—described at roughly $72 million—has seen about $63,000,000 spent so far. "That contract, we've spent about 63,000,000 of that," Anthony…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat