Middle school addition on schedule and under budget, district reports $9.89M spent to date

2477809 · February 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District reported the middle school addition is about 47.5% complete, with $9,890,483.36 expended (about 38% of the project budget); staff said the project is on time and under budget and that steel installation and exterior insulation work are underway.

Louisa County Public Schools staff updated the board on progress at the middle school addition, reporting the project is on schedule and under budget.

Staff said steel installation was due to start that week and showed recent exterior brickwork and upcoming exterior insulation and…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans