Middle school addition on schedule and under budget, district reports $9.89M spent to date
Summary
District reported the middle school addition is about 47.5% complete, with $9,890,483.36 expended (about 38% of the project budget); staff said the project is on time and under budget and that steel installation and exterior insulation work are underway.
Get email alerts on the Middle School Addition topic
No spam. Unsubscribe anytime.
Louisa County Public Schools staff updated the board on progress at the middle school addition, reporting the project is on schedule and under budget.
Staff said steel installation was due to start that week and showed recent exterior brickwork and upcoming exterior insulation and vapor barrier application. The presentation included interior shots and descriptions of second-floor classrooms, science labs, cafeteria and circulation elements.
Financial figures presented to the board put cumulative expenditures at $9,890,483.36, representing roughly 38% of the project budget. Staff reported the project was approximately 47.5% complete and said the district remained under budget, with contingency funds still available. A small required service to Dominion for a fire-pump connection of $2,046.86 was noted.
Board members asked about contingency use, staffing needs associated with the additional spaces and sitework; staff said additional personnel will be required but no major building adjustments are needed for the culinary/cafeteria setup. The board offered encouragement and no formal action was recorded on the update.