Commission approves $9 million county share for $28.33 million airport drainage project at Detroit Metro

2471067 · February 25, 2025

Get AI-powered insights, summaries, and transcripts

Sign Up Free
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Wayne County will provide $9 million toward a $28,332,376 airport drainage and sewer-runoff improvement project at Detroit Metropolitan Wayne County Airport after the commission approved an intergovernmental agreement with the Wayne County Airport Authority.

The Wayne County Commission approved an intergovernmental agreement with the Wayne County Airport Authority to help fund drainage and sewer-runoff infrastructure improvements at Detroit Metropolitan Wayne County Airport.

County staff described the total project cost as $28,332,376. Under the agreement, the Wayne County Airport Authority is contributing $9 million, other partners are providing $9 million, and the county will contribute $9 million from the general fund. Hassan Shaikh, director of economic development, told commissioners the county’s $9 million will be included later on the Ways and Means agenda for the required budget action.

Michael Jackson, senior vice president for economic development at the Wayne County Airport Authority, outlined the developer partnership and the technical purpose of the work. Jackson said the developer team comprises a local partner, the Sterling Group, and a national aviation-focused developer, Hillwood, working with FedEx on a related development. He said the scope includes expanding infrastructure to convey glycol collected from aircraft de-icing to a local sanitary facility rather than allowing it to flow downstream, as well as increasing stormwater capacity and extending infrastructure to permit winter stormwater diversion for de-icing operations.

Commissioners asked about reporting requirements, contractor selection and whether local firms would be included; staff said the airport authority will lead developer selection and that the county will receive monthly project reports and periodic updates to the commission. Shaikh said the county will cap its exposure at $9 million and that if project costs exceed the current estimate, the airport authority and private developers will be responsible for overruns.

Commissioners approved the agreement. The motion was carried.

Votes at a glance Motion to approve a two-year intergovernmental agreement (with a two-year renewal option) with the Wayne County Airport Authority for drainage and sewer-runoff infrastructure at Detroit Metropolitan Wayne County Airport: moved by Commissioner Palamara; supported by Commissioner Kenlock; motion carried (vote tally not specified).