Board approves $14.25 million for Reynolds Middle School phase 3 renovation

2453056 · February 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Prosper ISD trustees approved a $14,246,439 guaranteed maximum price to renovate two classroom areas at Reynolds Middle School, with the district planning to use additional portables to allow staged, in‑session renovations. Vote was 6–0 with one abstention.

The Prosper ISD Board of Trustees voted Feb. 26 to approve a guaranteed maximum price of $14,246,439 for phase 3 of the Reynolds Middle School renovation, covering a full classroom-area renovation in two building sections.

Dr. Bradley presented the project and explained the district will add portables and swing an entire wing into those temporary classrooms so the district can renovate while school is in session. He told the board that Reynolds currently houses about 1,700 students and that, unlike Rogers, Reynolds is not expected to see as sharp an enrollment drop when new middle schools open, so the district must phase work differently.

"This phase 3 for $14,246,439 is the complete renovation of Area 3 and Area 1 of the building," Dr. Bradley said, describing the work as floor-to-ceiling—new flooring, ceilings, furniture and technology upgrades.

Trustees approved the motion to accept the GMP. The vote passed 6–0 with one abstention; the transcript does not specify which trustee abstained.

Background: Reynolds opened in 1999 (as a high school) with an addition in 2002; the classrooms affected have not been renovated since those earlier construction phases, according to the administration. The administration said this phase will bring 50–60% of the building to a substantially modern condition; a phase 4 will follow later to complete the program.

Next steps: Administration will execute the GMP and add portables this summer to stage construction; a later phase will be brought forward for board consideration.