The county accepted low construction bids for a control facility project and identified roughly $300,000 to fund work — $200,000 currently available plus $100,000 from a 2009 SPLOST — with private donations boosting a new building fund.
Jones County commissioners authorized awarding low bids and advancing a county control facility project on Jan. 3 after staff presented an updated cost estimate.
Project manager Jason Risner told commissioners an updated estimate, including a 10 percent contingency, came to $285,746. He said the county had identified $200,000 already available and could draw an additional $100,000 from a 2009 SPLOST infrastructure line…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat