FCPS planning and construction details timelines for modulars, roofs and master plans
Summary
Assistant director for planning and construction gave the committee a monthly CIP update including modular classroom deliveries, roof replacements, James Wood renovations, and a Sarando (Sherando) High School master plan in development.
Kenny (assistant director for planning and construction) presented the committee’s monthly capital projects update at the Feb. 10, 2025 meeting, summarizing schedules and next steps for multiple FCPS projects.
Key near-term items: modular classroom deliveries and installation are scheduled for spring and summer. Kenny said civil drawings are complete for the Middletown modular project, electrical drawings had been sent to vendors and cost estimates were expected by the end of February; delivery for one modular vendor was tentatively set for April 1 with on-site work continuing through April and May and systems work…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat