Carrollton Elementary HVAC project to start spring; contractor recommends two additional air‑handlers at extra cost
Summary
Project team told the board the Carrollton Elementary HVAC replacement will begin mechanical‑room work in early spring with anticipated completion Aug. 25; a contractor recommended replacing two air‑handling units above the stage, which would add about $300,000 to the estimated cost but remain within budget.
Get email alerts on the Facilities And Capital Projects topic
No spam. Unsubscribe anytime.
The Carrollton Elementary HVAC replacement project is scheduled to begin spring work in the mechanical room, with fabrication and field measurements to follow and a planned turnover to contractors after graduation, the division’s support services staff told the school board on Feb. 13.
Support services staff said JR Mechanical — the low bidder — recommended replacing two air‑handling units (units 5 and 6) above the stage because those units are the most likely to fail after the main work is completed. The recommended change order would add about $300,000 to the project, lifting the estimate from $5.9 million to roughly $6.2 million; presenters said that increase remains within the project budget.
“Out of all of the air handling units that you have at Carrollton … these two are the most susceptible to fail,” the division’s construction presenter said in the update, explaining the rationale to avoid an early post‑construction failure. Construction progress meetings will be scheduled once or twice a month, and work on piping and fabrication is expected in spring.
The anticipated project completion date is Aug. 25, timed for school opening. Staff said administrators will be temporarily relocated if needed during work, with phone systems and other equipment moved to alternative locations. Presenters said they will coordinate staging, parking‑lot access, and the removal of personal items from the building with principals to ensure a smooth transition.
Why this matters: the HVAC replacement is a capital project intended to improve learning conditions and avoid repeated emergency repairs; adding the two air‑handling units now is presented as a risk‑mitigation step to avoid higher costs or outages soon after a major renovation.
What’s next: staff will finalize the contract documentation and issue change‑order details for board review if approved; construction will proceed through summer with periodic updates at board meetings.