City to forward HanHui Garden final acceptance and bench purchase to council amid $50,000 fundraising shortfall
Summary
FEDRAC on Feb. 25 forwarded final acceptance of the HanHui Garden boring project (final construction amount $40,746.45) and a $26,144.95 bench purchase to the March 4 consent agenda, while staff reported a roughly $50,000 fundraising shortfall for completing the garden.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
The Federal Way FEDRAC committee on Feb. 25 moved to forward two park items tied to the HanHui Garden project to the March 4 consent agenda: final acceptance of the garden boring work and authorization to buy 15 benches for the new garden.
Final acceptance and retainage: staff reported the final construction amount for the garden-boring work at $40,746.45 and recommended acceptance to allow release of retainage for the Small Public Works Project. The staff presentation said the contractor (recorded in packet as Landscape of Washington LLC) completed work per the scope and staff was pleased with the performance.
Bench purchase and funding: the Korean American Association raised $15,000 toward 15 benches; after consulting park standards staff determined the full procurement at current standards would total $26,144.95. Staff proposed the city fund the $11,144.45 difference from the capital projects fund and to purchase under the KCDA cooperative purchasing agreement with Northwest Playground Equipment Inc. Staff said the benches are six‑foot, backless style with center armrests per park standard to discourage sleeping and to meet durability expectations.
Funding shortfall for garden completion: council members and staff discussed an overall reported fundraising shortfall of about $50,000 for garden completion, noted by former Mayor Park. Staff said the city is in discussions with the Federal Way Korean American Association and that King County funds originally allocated (referred to in the record as a King County "lehi" amount) may be considered for backfill; staff said no city commitment had been made and that any city contribution would be brought through the parks committee for consideration.
Committee action: the committee forwarded both the final acceptance and the bench-purchase authorization to the March 4 consent agenda. The acceptance motion was recorded as carrying 2–0. The bench purchase motion was forwarded by voice vote.
Why it matters: the actions will enable staff to release retainage for work completed and to procure benches meeting city park standards; staff flagged a remaining project funding gap being worked with donors and the mayor’s office.