City highlights CIP projects: fleet decentralization, Fire Station 24 and solid-waste relocation among updates

2436645 · February 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff previewed a set of capital projects — including two fleet decentralization sites, South Howard flood relief, Fire Station 24, a TPD annex, solid-waste relocation, Fair Oaks recreation campus and water/wastewater system upgrades — and answered council questions on schedules and budgets.

Tampa — City infrastructure leaders gave City Council a biannual capital improvement update, highlighting a handful of major projects and answering council concerns about timelines and budgets.

Jean Duncan, infrastructure mobility administrator, said the city’s CIP viewer and OpenGov pages list scores of projects and that staff had selected several to spotlight: fleet decentralization and asset management sites, the South Howard flood-relief project, Fire Station 24, a Tampa Police Department Howard Avenue annex for evidence and forensics, the solid-waste transfer station relocation to 30th Street, the East Tampa Recreation Complex (Fair Oaks), and water and wastewater “pipes” upgrades.

Adri Colvino, director of logistics and asset management, described a decentralization initiative to place fleet maintenance closer to user departments; she said the Fortieth Street site (heavy equipment) is at 60% drawings with an estimated total project cost the presentation listed as “13.9” (staff clarified this was an estimate in millions). Colvino said the site will reduce vehicle downtime and expand service for heavy equipment operations.

Fire Chief Barbara Tripp said Fire Station 24 is planned on city-owned parcels near the Greco complex and estimated a full project cost of about $24 million; staff said the project is on a condensed schedule but cautioned scheduling is still being refined and that a kickoff meeting for final design was recently rescheduled.

Assistant Chief Patrick Mesmer briefed council on the TPD Howard Avenue annex, a renovated building to centralize evidence and forensics that the department says will reduce long‑term facility costs and consolidate evidence storage. Mesmer said design and permit submittals were completed in late January and the team expects bids and a Council award in June with a projected construction completion in late 2026; staff estimated a project budget near $40 million (includes soft costs and equipment).

Solid Waste Director Larry Washington outlined the transfer station relocation to 30th Street and the associated fleet and scale-house changes; the department expects ground‑breaking in March and a 2027 completion window. Washington said a CCNA selection for associated maintenance facilities will be held next week and that funding primarily comes from solid‑waste enterprise funds rather than general fund dollars.

Tony Mulkey, Parks and Recreation, said the new Fair Oaks Recreation Complex in East Tampa is under way with construction on the 33,000-square-foot community/senior center and athletic features; he said the project remains on budget and on schedule for phased opening later this year and into the following season.

Rory Jones (water) and Eric Wise (wastewater) reviewed pieces of the city’s multi‑year pipes program, including replacement of aging chemical disinfection systems and upgrades to dozens of wastewater pumping stations to make electrical systems flood‑resilient. Jones said on-site hypochlorite generators will begin commissioning in October with project completion by year-end; Wise said the city is accelerating repairs at seven pumps that flooded during recent storms.

Council questions focused on schedule specificity (calendar vs. fiscal year), funding sources and the ability to accelerate high‑priority projects; several members pushed staff to pare float from schedules, provide quarterly milestones and report back with tighter timelines and breakdowns of construction vs. soft costs.

Why it matters: The city is managing a large multi‑year capital portfolio that will require continued coordination of enterprise funds, grants and debt. Councilmembers said they want clearer quarterly targets and more transparency on “what’s in” each dollar figure.

Next steps: Staff said they will provide more precise quarter/phase timing in future briefings, monthly or quarterly updates for high‑priority public safety projects and additional public meetings for projects with neighborhood impacts.