Commission approves $645,425 emergency payment for North Interceptor lining, amends O&M contract and OKs $310,000 design change for Mothers Brook work
Summary
4 Rivers Sewer Commission authorized payment of $645,425 for emergency lining of about 4,000 feet of the North Interceptor, approved an amendment to the O&M agreement to codify use of the contractor for emergency work, and approved a $310,000 design change order to Woodard & Curran for related rail‑track work on the Mothers Brook project.
The 4 Rivers Sewer Commission on Feb. 26 approved an emergency payment of $645,425 to cover repair and CIPP lining work on the North Interceptor and approved an amendment to the operation-and-maintenance contract to clarify the contractor’s authority and compensation for out-of-scope emergency work.
Paul Furlan, the commission administrator, told members the work addressed multiple short, highly deteriorated sections on an 18-inch reinforced concrete pipe along the railroad corridor; roughly 4,000 feet of the interceptor were lined in several segments after a collapse eight months ago exposed reinforcement and caused…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat