Hot Springs seeks $96,687.50 change order for Whittington Avenue improvements

2413329 · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff requested a change order to a Gosley Construction contract for Whittington Avenue improvements to adjust quantities; the additional $96,687.50 would bring the project total to $845,966 and will be considered on March 4.

The City of Hot Springs presented a requested change order to the Gosley Construction Co. Inc. contract for Whittington Avenue improvements, adding $96,687.50 to align final quantities with available funding.

Assistant City Engineer Mike Hill told the Board the Whittington Avenue project (awarded by Resolution 10090 on Oct. 4, 2022) is funded by a FLAP grant and city funds and is intended to improve accessibility to Hot Springs National Park for the Whittington Valley neighborhood. Planned improvements include sidewalks, ADA ramps, crosswalks, rain gardens, bicycle lanes, a multiuse trail and intersection improvements.

Hill said work nearing completion produced a clearer picture of remaining quantities; the change order does not add new elements but increases quantities. The change order would add $96,687.50, bringing the contract total to $845,966. The resolution (R-25-42) is scheduled for formal action at the board’s March 4 meeting.

No vote was taken during the agenda session.