A public commenter asked whether Haslet’s water and sanitary sewer systems and a planned South Bus Pump Station are sized to serve future growth in the extraterritorial jurisdiction; city engineer Mike Anderson said the lines are sized to serve ETJ and city limits and described planned pump capacity.
Get email alerts on the Utilities Infrastructure topic
No spam. Unsubscribe anytime.
A resident raised capacity and future-proofing questions Tuesday about Haslet’s water and sanitary sewer systems and a planned pump station that the commenter called the South Bus Pump Station on FM 156.
The commenter said a previous presentation to the Capital Improvements Advisory Committee had suggested sewer and water lines were sized only for city limits, not for the extraterritorial jurisdiction (ETJ). Mike Anderson, identified in the transcript as the engineer, replied that the city’s water and sewer lines are sized to accommodate development in both the ETJ and the city limits.
Anderson also described the planned pump station’s design and capacity: the current build will receive future pumps when needed; the facility will include a 25-horsepower pump and other pumps operating at 50 horsepower with variable-frequency drives, and the system will include sensors in the lines. The transcript records the engineer saying the station is designed with space and infrastructure to accept additional pumps in the future.
The commission did not take action on the matter during this meeting; the exchange occurred during public comment and did not produce a directive or motion.