All Points Broadband outlines timeline for Frederick County fiber rollout and urges residents to verify addresses

2395425 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

All Points Broadband told the Board the county can expect last‑mile construction to begin in July, with cabinet lighting beginning in August and rolling customer activation starting early in the third quarter.

All Points Broadband provided a project update to the Frederick County Board of Supervisors Wednesday, describing current construction plans, permitting challenges and how residents can confirm whether their address is included in the funded network.

Jimmy Carr, representing All Points, said the county participates in a multi‑jurisdictional public‑private partnership that includes All Points, Dominion Energy Virginia and the Northern Shenandoah Regional Commission as the federal grant administrator. Carr said fiber construction is underway regionally and that in Frederick County the company has reduced the planned number of pole attachments to "under 3,000" across pole owners by converting many routes to underground placement to reduce make‑ready delays.

Carr gave target dates: last‑mile construction is planned to begin in July, construction will ramp up to roughly 17 miles per month with 6–7 crews, and activation (lighting of cabinets) is expected to begin in August with rolling service availability starting early in the third quarter. He said All Points will contact households about 60 days before service will be available in their fiber service area.

The presenter described state and federal funding changes that expanded eligibility: the federal broadband threshold has increased to 100/20 Mbps, and Virginia has a $1.48 billion BEAD allocation to reach additional eligible locations. All Points said it shifted about 19% of locations from one state funding program into another to preserve local budget caps and ensure coverage of intended locations.

"If you contact people too far in advance, when the service is actually available they don't sign up," Carr said, explaining the 60‑day outreach window. He urged residents to check APBfiber.com and Virginia's official broadband map at connectingvirginia.com and to contact county staff if addresses do not appear correctly. He also walked supervisors through the map color coding: funded locations, in‑project locations and BEAD‑eligible locations.

Supervisors raised specific concerns about addresses along major roads that do not appear on maps or appear outside planned service areas. Carr and county staff agreed to schedule one‑on‑one map reviews with supervisors and to provide materials staff can share on the county website to guide residents through checking APBfiber.com and the BEAD maps.

The presentation emphasized that the project's timing depends on permitting and make‑ready work with pole owners and VDOT permits; All Points said Dominion's middle‑mile construction is slated for substantial completion by year end and that SVEC has engaged USDA processes to add vendor capacity for make‑ready work.

No board vote was required for the update.