Board approves low bids for Prairie View and Sand Lake STEM labs; project over budget but within contingency
Summary
The Holmen School District board approved the consent agenda that included award of construction, HVAC, plumbing and electrical contracts for six elementary STEM labs at Prairie View and Sand Lake. Low bids totaled $217,092, $9,092 over the budgeted amount but within the district—s contingency funds; work is scheduled to begin this summer.
Get email alerts on the School Facilities Stem Labs topic
No spam. Unsubscribe anytime.
The Holmen School District Board of Education approved low bids for construction of STEM labs at Prairie View and Sand Lake elementaries as part of its consent agenda on Feb. 24.
District Director of Facility Services Chad Brando presented the bid results, saying the district received multiple bids across four scopes: general construction, plumbing, HVAC and electrical. "The combined total lowest base bids came to $217,092 which was over our budget by $9,092. We're still well within our contingency funds," Brando said.
Nut graf: The contract awards cover six new STEM labs (three at each school: K–1, grades 2–3, and grades 4–5). The board approved the consent agenda by voice vote; the district will use contingency funds to address the amount over the original budget.
Brando said contracts were solicited on Jan. 27 and opened Feb. 13. He identified the low bidders by scope: Americon (general construction), Cooley Regent Mechanical (HVAC), and B & B Electric (electrical). He characterized the bidding as competitive and said the district verified contractors— understanding of the project before recommendation.
Brando described basic phasing and logistics: work will start this summer, crews will erect dust walls to limit disruption and will sequence work to leave paths to exterior doors. Because Prairie View runs a summer school program and both sites host YMCA before- and after-school care, staff are coordinating with those programs to maintain services while construction proceeds.
Discussion vs. decision: The board received the bid report and accepted the package as part of the consent agenda. No separate roll-call on the STEM bids was taken; the consent motion passed by voice.
Ending: Staff said final scheduling and coordination with summer programs will continue; construction sequencing and contractor coordination were described as part of the facilities plan.