Lakeland Healthcare Center work advances; county discusses drainage, permits and CIP sequencing
Summary
County construction staff reported demolition and permit progress at Lakeland Healthcare Center, described courtyard drainage fixes, previewed government-center parking bids and outlined capital improvement planning and equipment-surplus work.
County construction staff told the Walworth County Public Works Committee on Jan. 25 that demolition and early-construction work at the Lakeland Healthcare Center is underway, but one storm-sewer permit from the State of Wisconsin remains pending.
Nicole, a construction staff member, said the project team had begun demolition and secured most permits, but the storm-sewer permit review was scheduled for Feb. 18. “We received the plumbing permit. We received the DHS permit. We did not get the storm,” Nicole said. She added that part of the submittal process involved coordination with the City of Elkhorn.
Why it matters: Permitting affects schedule…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat