City plans 6‑week repair of failing Fry Boulevard sewer interceptor; 2.5‑week closure of Fry expected

2390431 · February 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Wastewater staff reported a sagging 10‑inch vitreous clay interceptor under Fry Boulevard that requires repair; the city plans a 6‑week construction window with a 2.5‑week full closure of Fry/Bridal Boulevard segment before ADOT paving.

Bryce Kirkpatrick, external operations manager for the wastewater division, told council crews are cleaning a 10-inch gravity-fed vitreous clay sewer interceptor under Fry Boulevard near the State Route 90/92 intersection because a sag in the pipe has worsened. The line serves roughly 140 acres of residential and commercial connections; maintenance crews are currently cleaning it at least twice a month to prevent backups.

Kirkpatrick said crews have observed additional settling and longitudinal cracks upstream and downstream of the sag. Because the interceptor is vitreous clay…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans