Developer outlines plan for 154 Miami Avenue; sewer main extension and rezoning to R‑3 are key hurdles

2387913 · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Iconic Homes and its engineer told North Bend council members the 154 Miami Avenue project will require about 930–950 feet of new sanitary sewer main and a rezoning from B‑1 to R‑3; the developer and village agreed to coordinate any sewer construction with the village’s planned Miami Avenue paving.

A development team representing Iconic Homes told the North Bend Village Council on Feb. 24 that a proposed residential project at 154 Miami Avenue will require a sanitary sewer main extension and a rezoning from B‑1 (commercial) to R‑3 (residential multifamily) for the site to be built as planned.

Jason Lane of Iconic Homes introduced engineer Tim Dwire of Open Architecture, who described early engineering work and a sewer-availability inquiry to the MSD (metropolitan sewer district). Dwire said MSD indicated capacity exists in the regional system but that the nearest sanitary sewer is not close enough to the property and would require an extension. "In order to achieve that, we're gonna need approximately 930 to 950 linear feet of sewer mainline extension," Dwire said.

Dwire said the developer will build the sewer main to MSD specifications, after…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans