Peoria County reports near-final costs for Health & Human Services building; project finishes under budget
Summary
County staff told the board that the Health & Human Services building opened early and is about $783,000 under the $22.9 million budget, with roughly $1.45 million still outstanding and $1.3 million held as retainage from the contractor.
Peoria County officials reported near-final financials for the Health and Human Services building, saying the project finished about a month early and is currently under the approved budget.
At the committee meeting Heather, a county staff member, told the board, "we are thrilled to report that, not only did the project come in 1 month early ... but it was also well on track to finish well under budget." Heather said the county's total approved budget for the project was $22,900,000 and that the county has spent about $20,700,000 to date, with approximately $1,450,000 outstanding on open purchase orders or pending expenses. Of the total, roughly $1,300,000 is being held as retainage by the contractor.
The report listed the original funding sources the board approved in April 2023: $4,950,000 from the health department (including $4,700,000 built in reserves and a $250,000 installment from the solid waste…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat