Augusta County broadband hookups delayed as make-ready permitting with VDOT stalls under Route 42

2385864 · January 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Work to connect initial broadband customers was delayed after providers discovered an unanticipated VDOT height/permitting requirement for crossing Route 42, forcing a bore-under permit and postponing planned December hookups; supervisors urged closer contract oversight.

Augusta County supervisors heard an update that fiber hookups planned for December were postponed after broadband contractors discovered a permitting obstacle with the Virginia Department of Transportation when attempting to cross Route 42.

A company representative and supervisors said make-ready work had been funded (county draw of about $1.7 million cited for…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans