County to pay $7,417 for ground prep at future fire station pad after value-engineering decision
Summary
VMS chief Frank Burrow told the commission that a value-engineering decision and acceptance of a bid alternative resulted in $7,417 of ground-prep costs for a planned third bay on a future fire station pad; staff said the price reflects ground-prep work not originally bid into the contractor package and will be covered in the project budget.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Frank Burrow, chief of VMS, briefed commissioners during the study session about a $7,417 net cost related to ground preparation for a future fire-station pad.
Burrow explained that bidders had offered a bid alternative to add a third bay on the planned station; when the board elected to accept the bid alternative, materials were obtained and ground prep was completed. Because the original bid packaging separated ground prep as a line item, the county now owes the ground-prep cost that was not included in the contract’s initial base bid. Burrow characterized the $7,417 as the ground-prep expense that must be paid to reconcile the bid alternative and ground-prep work.
Staff said the contractor would be asked to set a work date (March 5 was discussed) and that an additional change order related to winterization of concrete could be forthcoming. Commissioners asked about contingency and change-order controls; staff explained differences between design-bid-build, design-build and construction-manager-at-risk contracting approaches and said some change orders are unavoidable.
Outcome: Commissioners were advised of the $7,417 net cost and discussed scheduling and contingency management. Staff indicated the cost is within project budget allowances and will be processed as part of project close-out. No roll-call vote was recorded in the study session transcript.