Miami County moves closer to KDHE loan for sewer improvements; funding mix and easement status outlined
Summary
County staff told commissioners they will seek a formal resolution authorizing construction of sewer treatment and disposal improvements and that a KDHE loan in the range of $550,000–$600,000 is likely after bids; staff also said the county’s remaining ARPA contribution should be listed as $1,250,000.
Get email alerts on the Infrastructure Finance topic
No spam. Unsubscribe anytime.
County staff updated commissioners on the schedule for authorizing sewer‑treatment and disposal improvements and the paperwork needed to proceed with a Kansas Department of Health and Environment (KDHE) loan.
Staff said bond counsel recommended a formal county resolution authorizing the project before signing a KDHE loan agreement. The presentation included a funding table staff said would be corrected before the afternoon meeting: the county contribution line should show remaining ARPA funds of $1,250,000 (staff said the county contribution comprises $1,000,000 of county funds plus $250,000 of Spring Hills ARPA funds), and the project total would be adjusted to $4,564,126.
Staff estimated the KDHE loan portion likely would be in the $550,000–$600,000 range once the project is bid; the final loan amount will depend on bid results and market interest rates. Staff noted the bid should not go out until funding partners (KDHE, USDA Rural Development, Department of Commerce/CDBG) are on an assured footing; recent federal funding pauses could affect timing. The presentation also noted four remaining property easements to secure; staff said they expect to acquire three voluntarily and may have to use condemnation for one if negotiations fail.
Staff asked the commission to place the authorizing resolution on the afternoon agenda. County representatives said they would finalize the schedule and corrected figures before the action meeting and would publish required notices.
Why it matters: The resolution and loan work are central to advancing sewer infrastructure and meeting consent‑decree requirements while coordinating multiple funding sources. Easements and final bid results will affect the loan size and project timing.