Washington County officials outline storm recovery needs: Corby Bridge, roads and FEMA timeline
Summary
County leaders described millions in storm damage, emergency and long-term projects — including a $27 million estimate for Corby Bridge — and said FEMA reimbursement could take years while design and bidding begin.
Get email alerts on the Disaster Recovery topic
No spam. Unsubscribe anytime.
Washington County leaders on Feb. 24 detailed the scope and cost of recovery work after a recent storm, describing damage to roads, bridges and private property and laying out a multi‑year plan for FEMA reimbursement and reconstruction.
The presentation — delivered during a regular meeting of the Washington County Board of Commissioners — included a county estimate of $40 million to $60 million in overall damages, specific project budgets, and an explanation of the FEMA reimbursement process and local cost-sharing.
County mayor said FEMA has already provided direct individual assistance and that larger public works funding is in progress. "To date, as of last Thursday specifically, FEMA has put $6,482,000 into the hands of individuals in Washington," the mayor said, summarizing the federal aid delivered for housing, temporary rental assistance and other immediate needs.
Why it matters: the county faces urgent infrastructure repairs — roads and a major bridge were washed away — and must start engineering and bidding before long projects can proceed. Officials said some projects will be entirely federally funded because of the emergency designation but many will require careful documentation to secure reimbursements.
What officials told the commission - Consultant Alan Bach of IEM told commissioners the county is compiling damage estimates to obligate FEMA funds and pushed for rapid, audit‑ready documentation. "We're looking somewhere between $40 and $60 million in damages that we're putting in for," Bach said, adding that closure could take years for final settlement. - Paul Buck of the Washington County Soil and Water Conservation District reported the district secured $3.8 million in contract funding in 2024 for local projects and provided an initial estimate of $18.3 million to hard‑armor 18 erosion sites (9,815 feet) through the Emergency Watershed Protection program. Buck said those designs are under review by federal engineers.
Major projects and cost estimates discussed - Corby Bridge: County and Tennessee Department of Transportation engineers recommended full demolition and replacement; county estimate discussed in the meeting was about $27,000,000. TDOT's recommended rebuild would include current codes and specifications, not just replacement in kind. - Other roadway and site work: roughly $12.5 million listed for smaller roads and repairs. - Highway department relocation to the county farm: $1.7 million. - Solid‑waste relocation to a former highway site: estimated $1.5–$2.5 million. - County summary: commissioners and staff totaled the immediate near‑term reconstruction estimate at about $48 million for the projects discussed.
Obligations, reimbursements and timing - County staff reported FEMA typically funds 75% of approved eligible expenses, the state 20%, and the county 5%. County officials said volunteer hours, donated materials and documented in‑kind contributions can be credited against the local 5% share. - Alan Bach said the county expects to get funds obligated to Tennessee Emergency Management Agency (TEMA) in the coming months, but cautioned that final closeout of large disasters can take years: "That could take anywhere from one to two to three to four years before it's finalized." - The county reported two projects already obligated or soon to be obligated: $2.5 million for an initial Porta‑Bridge/design rapid project and a $5.1–$5.2 million obligation anticipated for the Little Germany Road rebuild.
Private property and tax relief Commissioners asked about land that was washed away along river corridors. Officials said some parcels have lost so much soil that traditional reconstruction — including septic systems — is impractical. The county is pursuing tax‑relief measures and grant options to purchase or otherwise assist owners of lots that have become largely riverbed; officials said the county may take title to blocks or individual lots as federal programs permit.
Next steps County staff said engineers and designers are working now so projects can go to bid when funds are obligated. Officials urged careful recordkeeping to pass FEMA audits and said legislative emergency funds recently authorized by the state and federal programs may cover interim financing and interest for projects where the county must borrow before reimbursement.
The commission did not vote on specific construction contracts at the meeting; staff said design work and obligated grants will be used to move some projects to bid in the coming months.