Council approves $21,536 change order for West Main Street phase 2

2382822 · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 2 to add service installations to West Main Street Phase 2 at a cost of $21,536.40, with the charge identified to the water fund and contractor Joker's performing the work.

The Festus City Council approved Change Order No. 2 for the West Main Street Phase 2 project, adding service installations with an additional cost of $21,536.40 charged to the city's water fund.

City staff told the council the added installations allow the contractor to complete service connections up to the meter and will let city crews continue concurrent work on North Second Street. Staff said Joker's discovered the missing service connections in the field and the change order captures those items that were not called out on the original plan set.

A staff representative said, "This ties into the last change order...the additional cost is $21,536.40." Council asked whether the cost would come from the water fund; staff confirmed it would.

Council moved and seconded approval; a roll call vote recorded members present voting yes and the motion passed.

The change order does not alter the project scope beyond the service installations described; staff indicated the work was needed to complete meter connections and avoid separate future mobilizations by the contractor.