District construction updates: South Terrebonne, Allender demo, Oak Lawn lobby and security projects reported
Summary
District staff and contractors reported progress on multiple reconstruction and renovation projects, including South Terrebonne High School, Allender demolition, Oak Lawn Middle School lobby completion, and several security and fencing projects. Timelines, asbestos/abatement notes, and next steps were described.
Get email alerts on the Construction Updates topic
No spam. Unsubscribe anytime.
District construction and facilities staff provided updates on ongoing projects across the parish, reporting progress at South Terrebonne High School, demolition and early work at Allender, completion of Oak Lawn Middle School’s secure lobby and the status of several security fencing and canopy projects.
Key updates
- South Terrebonne High School: Construction is progressing on interior finishes and mechanical systems; ceiling grids and prime coats are being installed and chilled-water piping and air handling work is under way. Contractors began removing quarry tile in bathrooms and are preparing locker rooms and other areas for reinstall. The presenter reported that the contractor began work after approval of prior change orders for windows and quarry tile.
- Allender (demo): The design/contract team said demolition is five months in and that roughly one-third of the slab has been removed. The team is cutting piles to six feet below the finished slab and preparing to bring in fill to elevate portions of the site in advance of reconstruction.
- Oak Lawn Middle School secured lobby: The secure lobby project was substantially complete and inspected by the fire marshal on Feb. 10; the contractor issued a punch-list contract and staff expect the work to be wrapped up soon.
- Security and fencing projects: Staff reported the Coach O’Bayou Blue parent drive is operational and can stack “almost 60 cars” in the new loop; chain-link fencing work is underway at Mulberry, Lisa Park, Evergreen and H.R. Bourgeois with an April completion target for some elements. Roof and canopy work at several other schools continues on schedules reported by staff.
- Asbestos/abatement: Board members asked whether South Terrebonne will be free of asbestos after reconstruction; staff said areas touched by the reconstruction will be asbestos-free but that some peripheral areas outside the scope may still require abatement later.
Selected direct quote from the progress briefing:
- “Ceiling grids are going in... prime coats have been applied to majority of the Second Floor walls... the contractor started basically this week after y'all approved the last 2 change orders for the windows and the quarry tile.” — project update speaker on South Terrebonne progress.
Why it matters: The updates document reconstruction progress on major multi-year projects and the district’s security upgrades, affecting students’ learning spaces, staff operations and project timelines tied to reimbursements and contract schedules.
Next steps: Teams will continue demolition, fill and elevation work at Allender, complete punch-list items at Oak Lawn, finish fencing and canopy work and bring updated cost/schedule information to the board as work progresses. Staff noted some schedule sensitivity where cultural-resources or abatement processes remain active.