Construction update: REACH and ECC facilities progressing; target completion for REACH in November

2377078 · February 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District construction manager reported REACH facility is ahead on classroom wing work and on schedule for a November completion; ECC alternates may finish by late year or early next year. Board also discussed early-childhood-center naming options.

The Wentzville R‑IV Board received a construction update Feb. 20 on the REACH facility and the Early Childhood Center (ECC). Contractors reported progress on classroom wings, mechanical systems and storm-shelter construction.

The district’s construction representative said the two classroom wings are enclosed and that interior work including metal stud framing, piping, ductwork and electrical is underway; those wings were described as roughly two to three months ahead of schedule because interior work can proceed despite winter weather. The project includes four storm-shelter areas built to ICC-500 standards for high-wind protection.

Budget and schedule: The speaker reported the overall project was approximately 84% complete at the time of the update and that the REACH facility remained on schedule for a November completion; alternates that include additional ECC classrooms were tentatively expected by late winter or early the following year. The presenter noted some expected change orders for hardware and access-control coordination, but said the project team was managing change-order risk.

Naming discussion: The board reviewed public suggestions for naming the early-childhood facility. Members discussed policy that would apply if the board names the building for an individual; the policy requires documentation and a nomination process. No decision was made at the Feb. 20 meeting.

Next steps: Administration will schedule a site tour once weather warms and provide continued budget and schedule updates to the board.