Crescent City, Palatka school projects 48% complete; contingency, furniture and timelines discussed
Summary
Contractors told the Putnam County oversight committee that construction on Crescent City and Palatka preK–6 campuses is about 48% complete, contingency balances are positive and staff are selecting fixtures, furniture and equipment with a roughly $2 million furnishing budget.
Contractors and district staff reported steady progress Tuesday on the Crescent City and Palatka preK–6 school projects and said contingencies and contract allowances currently leave the district in a stable position.
At a Putnam County School Capital Oversight Committee meeting, Bill Elliott, senior project manager with Ajax, said the Crescent City campus is being built under a guaranteed maximum price and that the construction team has produced regular progress videos. “We’re fortunate enough to be building the Crescent City PK–6, and, I don’t really have anything but good things to say,” Elliott said.
The project team said overall completion stands at about 48%, with framing and above-ceiling mechanical, electrical and plumbing work largely underway. Ken Ausley and Todd Duffy, who presented the site update, said the roof is dried in, windows are going in and interior finishes such as drywall and paint are advancing. Ausley said crews will begin Brandy Lane road work next week to prepare the bus access off the site.
Why it matters: The two campuses are part of the district’s…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat